K-IV Water Project Delayed Again as Completion Target Shifts to June 2027

WAPDA officials told a National Assembly sub-committee that Karachi's K-IV bulk water supply scheme, first conceived in 2003, is now expected to finish by June 2027, prompting lawmakers to demand accountability for repeated delays.

around.pk·6m ago

Karachi's long-stalled Greater Karachi Bulk Water Supply Scheme, commonly known as K-IV, is now expected to be completed by June 2027, officials from the Water and Power Development Authority (WAPDA) informed a National Assembly sub-committee on Wednesday. Lawmakers questioned the recurring delays and pressed for accountability over the project's slow pace, according to the briefing.

The sub-committee of the National Assembly Standing Committee on Water Resources, chaired by Muhammad Idrees, reviewed the project's implementation, design complications, planning and the reasons behind the setbacks. Members voiced concern over the prolonged execution of the scheme, stressing that it is critical to meeting Karachi's growing water needs and that no further delays should be tolerated. They also asked for details of action taken to fix responsibility, noting that both the federal and Sindh governments have attached high importance to the project.

WAPDA officials said the scheme was conceived by the Sindh government in 2003 to address Karachi's rising demand for potable water and to reduce its supply deficit. Civil works began in July 2016 under a contract awarded to the Frontier Works Organization (FWO), but the original December 2018 completion deadline was missed after design-related problems surfaced. A third-party investigation commissioned by the Sindh government later identified shortcomings in the design.

The federal government took up the project under the Karachi Transformation Plan in 2020, while WAPDA assumed responsibility in April 2021 and began mobilisation in September 2022. The scheme was initially scheduled for completion by October 2023, but its revised target now stands at June 2027. Officials said the revised design and planning have been submitted to the Planning Commission and the federal government.

Originally planned to deliver 650 million gallons per day (MGD) from Keenjhar Lake in Thatta to Karachi in three phases, the scheme envisages 260 MGD under Phase-I, another 260 MGD in Phase-II and 130 MGD in Phase-III. The first phase, being executed by WAPDA under the Ministry of Water Resources, is designed to supply 260 MGD through three termination points at Pipri, North East Karachi and Manghopir. The repeated slippage in deadlines has made K-IV a focal point of concern for the city's water-stressed population.

The story so far Water and Power Development Authority (WAPDA)

  1. Unannounced Evening Power Cuts Hit Lahore as Tarbela Faults Cut Supply
  2. Supreme Court Sets Eight Grounds for Cancelling Bail in Landmark Judgment
See the full timeline →

Continue the story

View all →

Read more