Punjab Set to Open Two Rawalpindi Underpasses by December
The Race Course Park and Charing Cross underpasses in Rawalpindi have reached 75% completion and are on track for a December opening, part of a wider 25-kilometre signal-free corridor.
Get this story and every big update first on WhatsAppFollow the around.pk English News channel — free, no spam Follow
Two underpasses in Rawalpindi have reached roughly 75% completion, with officials expecting both to be finished by the end of December. The projects at Race Course Park and Charing Cross are being built by the Punjab Highway Department, according to a senior district administration official.
The Race Course Park underpass will carry two lanes of northbound traffic and includes a three-level road design intended to ease vehicle movement and turning. The Charing Cross underpass will serve southbound traffic through two lanes, supported by two-level road lanes. Both structures form part of a planned signal-free corridor between Koral Chowk and Motorway Chowk.
Work is also under way on Peshawar Road, where the highway department is rehabilitating and widening the stretch between Bungalow No. 276 and Raffay Mall. Utility services are being moved underground to clear roadside obstructions and improve the flow of traffic.
The two underpasses are part of a broader 25-kilometre signal-free corridor linking Koral Chowk with Motorway Chowk. The wider plan includes the completed remodelling of Kutchery Chowk and the construction of the General Post Office underpass.
Other agencies are contributing to the corridor. The National Highway Authority is rehabilitating the road between Motorway Chowk and Chur Chowk, while the Rawalpindi Development Authority plans to rebuild Old Airport Road between Koral Chowk and Ammar Chowk.
The Punjab government aims to complete the entire signal-free corridor by June 2027. Once finished, the project is expected to cut travel time between the Islamabad Expressway and Motorway Chowk to between 15 and 20 minutes.
The story so far National Highway Authority
- Punjab Highway Department Completes Rs3 Billion AFIC Underpass Design, Awaits Provincial Approval
- Landslide Blocks Kaghan Highway, Stranding Tourists and Residents
- Federal Development Spending Stalls at 10% of Annual Budget in First Four Months